The pre-treatment system was constructed in order to reduce the concentration of fat and oil originating from the Carcass disposal facility sewage flowing to the wastewater treatment plant belonging to Kibbutz Ginegar.

Detailed process

Implementation of the emergency facility included the construction of:

  • 2 multi-stage chemical reactors.
  • Inlet Pipe going from the pipe exiting the Carcass disposal facility, to the top of container A – the aerobic reactor.
  • Separation valves and pipe drain.
  • Air dispersion system using floating diffusers for uniform distribution of air in the reactor.
  • Sludge recirculation pump moving material between the bottom of the sediment and the aerobic rector.
  • 2 blowers supplying air at a capacity of 550 m3/h each.
  • Main electrical panel for the system.
Project Details
Location
Jezreel Valley
Israel
Field
industrial wastewater
Description
Preventing the flow of abnormal loads to the regional fire station by a system with integrated technologies
Client Name
Ha'emek Carcass disposal facility
Main Figures
Pre-Treatment System for Carcass Disposal Facility
Budget
0.6 Million NIS